Friday, August 12, 2011

The utility contractor (Humir) has completed a majority of the utility work on this project with only chimney seal installation and utility punch list work remaining.
Arrow Road Construction is scheduled to resume and complete asphalt paving next week on Virginia, Bianco, Crabtree, Royal Oak, Sandford, Pine, Brett, Lizette and Potter.