The utility contractor (Humir) will continue with utility work for the resurfacing streets on Virginia Lane this week and Crabtree Lane next week. The concrete contractor (Suburban) will finish curb and gutter and sidewalk construction on Lizette Lane and Brett Lane this week. Next week, Suburban will resume concrete work on Potter Lane, Knollwood Lane, Linneman Street, Virginia Lane, Bianco Terrace, Royal Oak Lane, Sanford Court and the Meadowview subdivision streets.

Arrow Road Construction will be complete with a majority of the Minor Area Repair Strategy (MARS) program except patches on Pine Street and Pebbleford Drive. The MARS Program is a program in which only isolated pavement repairs (patches) are made (repairing the most severely deteriorated pavement) to a street to extend the life of that street until more extensive repairs such complete resurfacing or reconstruction can be completed.