Friday, June 10, 2011

The utility contractor (Humir) will continue with utility work for the resurfacing streets on the west side of the Village (including Potter Road, Lizette Lane and Brett Lane) next week. The concrete contractor (Suburban) is scheduled to begin curb and gutter and sidewalk replacement on the west side of the Village next week.

Arrow Road Construction has completed a majority of the Minor Area Repair Strategy (MARS) program on the east side of the Village this week. Arrow Road Construction will continue with the Minor Area Repair Strategy (MARS) program on the central portion of the Village next week. The MARS Program is a program in which only isolated pavement repairs are made (repairing the most severely deteriorated pavement) to a street to extend the life of that street until more extensive repairs such complete resurfacing or reconstruction can be completed.